26 June (Part 2) - Crossrail gets ready for utility diversion
Before Network
Rail can start building Abbey Wood’s station, water, gas, electricity and
telecommunications services must be diverted around the site. The conduits under
the railway line were finished a month ago and the new
Felixstowe Road is
rapidly emerging. Now it’s Gayton Road’s turn. These pictures show progress over the last two weeks
And now for something very different; the concrete laying machine which will
construct the track bed through the tunnels waits in Plumstead sidings.
Delivered by road because rail access is not yet complete.