30 July (Part 3) - Crossrail accelerates

Crossrail CrossrailAbbey Wood’s Crossrail developments are about to enter a dramatic new phase. The line will be closed for seven weekends out of eight, there is a lot going on.

The utility diversion in Gayton and Felixstowe Roads should be completed within the next couple of weeks clearing the way for construction of the new station.

A new Bostall Manorway footbridge is due to be installed on 23rd August (see below), prefabricated and the job should be done in a day. The old bridge will remain in place until the new one is ready for use.

The new North Kent line platform is getting longer by the day.

Further down the track the connection to the new Plumstead sidings is very nearly made.

Crossrail Crossrail Crossrail Crossrail

 