Upper Wickham Lane/Okehampton Crescent - Statement of progress of works
As you may be aware, construction works to the roundabout was suspended
following a routine inspection by Council engineers, which identified faults
with the design consultants layout that needed to be rectified. An
investigation into the design faults was undertaken and a revised design ordered
to enable the contractor to complete the scheme. The revised design took longer
than anticipated, as it required the design of a retaining wall to ensure that
the new works would fit into the cramped space available because of underground
services and equipment in the area.
The revise design was received and approved
by the Council on the 7th October, and the Contractor re-started work on the
11th October. The outstanding works are expected to be completed within seven
weeks, although due to the nature of the works involved, this is heavily
dependent on the weather. The Councils Implementation Team have been working
closely with the contractor to ensure the work is carried out quickly, but also
safely, and the level of workmen and weekend working has been agreed to achieve
this.
To complete these works, the temporary traffic signals will need to remain
in operation, and the Council can only apologise if you have been inconvenienced
by them.